The ResinTech RMS system: a seamless liquid membrane, reinforced with fabric over the full surface, laid over a sound existing flat roof or a new concrete roof deck. Every roof is inspected, and every existing roof is test-patched, before we quote the full job.

Restore or replace

If the roof is sound, it may not need to come off.

A flat roof that leaks is not always a roof that has to be torn off. Where the existing roofing is still dry, sound and firmly bonded to the deck, and the roof drains, it may be restorable in place, subject to an adhesion test patch: the wet and failed areas repaired, every seam, drain and flashing detailed, and the field sealed under a seamless, fabric-reinforced membrane. The sound roofing stays where it is and becomes the substrate.

Where the roof is not sound, we will say so. Roofing that has lost its bond across the field, a deck that is wet throughout, or a roof that holds water after rain is not fixed by a coating, and the honest answer is replacement, which we provide as torch-on roofing, or new drainage first. The inspection and the adhesion test patch decide which side of that line your roof is on, before you are asked to commit to anything. Our article on restoring or replacing a commercial flat roof sets out the questions that decide it.

We work across Greater Vancouver, from Vancouver, Burnaby, Richmond and Surrey to the North Shore, out into the Fraser Valley, and in the Sea-to-Sky corridor and Greater Victoria. Commercial and industrial roofs come first: warehouses, plants, retail and office buildings. Residential flat roofs, strata buildings and new concrete roof decks follow the same process.

Who it is for

Roofs that keep the weather out, not roofs people walk on.

ResinTech RMS is a liquid-applied waterproofing membrane for flat and low-slope roofs on commercial, industrial and residential buildings. It goes on new concrete roof decks, and over existing flat roofing that passes an inspection and an adhesion test patch. It is not a traffic surface, so the parts of a roof that people walk or drive on regularly take one of our traffic systems instead.

Which system goes on which roof
The roofWhat goes on it
Commercial or industrial flat roof on a new concrete deck, with or without occupied space belowRMS, with the reinforcing fabric over the full surface
Residential concrete roof deck over living space, a garage or parkingRMS, with the reinforcing fabric over the full surface
Existing flat roofing on a commercial, industrial or residential buildingRMS after an inspection and an adhesion test patch, with the reinforcing fabric over the full surface
Roof terrace, or a walkway route to rooftop equipment with regular foot trafficResinTech PTS+ pedestrian traffic system, not RMS
Rooftop parking over occupied spaceResinTech VTS-D+ vehicular traffic system — see parkade waterproofing
New wood or plywood roof deckContact us to assess; new wood and plywood decks are not covered by the RMS data sheet

The system

Two coats, one fabric, one top membrane.

The waterproofing is two coats of ResinTech FPU with a polyester reinforcing fabric between them. FPU is a flexible, crack-bridging polyurethane with 800% elongation and flexibility down to −35 °C. It stays tacky for days and is not made to face sun or traffic, so it is always covered with a UV-stable top membrane once it can be recoated, typically 8–12 hours after the last FPU coat, and within 72 hours. How each layer works is explained in our article on fabric-reinforced liquid roof membranes.

Illustration: the ResinTech RMS roof membrane, layer by layerFrom the top: PPM top membrane, second FPU coat, polyester reinforcing fabric, first FPU coat, primer only where needed, and the roof itself. Not to scale.PPM top membraneUV-stable polyurea, medium grey: one coat, up to20 mils wet filmFPU, second coatEncapsulates the fabricPolyester reinforcing fabricOver the full surface; laps at least 3 in at thesides, 6 in at the endsFPU, first coatFlexible, crack-bridging polyurethane; detailsdone firstPrimer, only if neededResinTech CBE or TUE, where the substrate or testpatch calls for itThe roofA sound existing roof, or a new concrete deck
Illustration, not to scale: the RMS layers as we build them, with the fabric over the full surface. The colours only tell the layers apart; PPM is grey.
The RMS build, layer by layer (wet film per coat)
LayerProductWet filmWhat it does
Primer, only if neededResinTech CBE or TUEPer the primer data sheetUsed only where the substrate or the test patch calls for it
Base coatResinTech FPU (FlexCoat-PU)Set in our written specificationFlexible, crack-bridging polyurethane, applied after the details are done
ReinforcementPolyester fabric, one layer—Full surface on every RMS roof, concrete deck or existing roofing, and always at seams, laps, flashings, drains and transitions
Second base coatResinTech FPUSet in our written specificationEncapsulates the fabric; it can go on wet-on-wet as the fabric is laid
Top membraneResinTech PPM polyurea, or HPP polyasparticPPM: one coat, up to 20 mils. HPP: set in our written specificationCovers and protects the FPU, which is not made to be left exposed
Colour finish, optionalResinTech HPP or TCU over PPMPer the product data sheetWhere a set colour or gloss is wanted

Every coat is checked with a wet-film gauge and the film builds are recorded. Product data on this page comes from the ResinTech RMS System Data Sheet (RT-RMS Rev. 1.0) and the current product data sheets; the film build for your roof is set in our written specification. Ask us for a copy.

FPU elongation
800%
Low-temperature flexibility
−35 °C
Top membrane on
After 8–12 h, within 72 h
Fabric laps, minimum
3 in sides, 6 in ends

How a roof job runs

Inspect, test, detail, coat, top, hand over.

  1. Inspect the roof.

    The substrate, the drainage, the moisture condition, and every joint, drain, upstand and penetration. A roof that holds water after rain needs its drainage corrected first: RMS needs positive drainage.

  2. Apply a test patch.

    On an existing roof, a small area is cleaned, repaired and dried as it would be for the full job, a patch of the system goes down and cures, and its adhesion is checked before the full job is quoted. The existing roof type is confirmed with ResinTech at the same time.

  3. Prepare and detail.

    Existing roofs are cleaned, loose granules and failed coatings removed, and splits, blisters, open laps and wet areas repaired and dried. Concrete decks get a minimum 28-day cure, lose their laitance, oils, curing compounds and loose coatings, have high spots ground, and have holes and cracks repaired. Then drains, upstands, wall junctions, penetrations, corners and seams are reinforced with FPU and fabric before the field coats. Expansion and movement joints get their own joint detail.

  4. Lay the FPU and the fabric.

    The first coat at the specified wet film, the fabric rolled into it over the full surface while it is fresh with laps of at least 3 in at the sides and 6 in at the ends, and the second coat either straight over it, wet-on-wet, or 8–12 hours later. The membrane is then inspected for pinholes, voids, exposed fabric and thin spots, and repaired before moving on.

  5. Put the top membrane on.

    PPM, or HPP where the roof has to take light foot traffic sooner, applied once the FPU can be recoated, typically 8–12 hours after its last coat, and no later than 72 hours after it.

  6. Hand over.

    The roof is kept closed and protected from rain until it cures. Batch numbers, film builds and weather are recorded, the finished roof is inspected for pinholes, thin spots and damage, and the record is yours.

The top of a planter coated in ResinTech FPU and PPM up to the building wall, the membrane still glossy

Detail work in the same products: ResinTech FPU under a PPM top coat, carried up the building wall on one of our planter jobs. A planter, not a roof. See the project.

System
ResinTech FPU and PPM
Work
Planter waterproofing
Location
Not recorded

The work runs in dry, stable weather only, with the roof surface at least 3 °C above the dew point and never damp, frozen or contaminated. FPU needs a surface between 5 and 35 °C; HPP needs a surface of 10–30 °C, air of 10–32 °C and humidity no higher than 85%. For a first look at your own roof, use our flat roof inspection checklist.

PPM or HPP on top

Grey PPM as standard, HPP for other colours.

The top membrane protects the FPU underneath; the FPU and fabric do the waterproofing. PPM is our standard and preferred top, and it comes in grey only. HPP is the alternative when the owner wants another colour, and it also takes light foot traffic sooner (3–4 hours at 23 °C). Where a set colour or gloss is wanted over PPM, an HPP or TCU colour finish can go on top.

The two top membranes compared (typical values)
PPM — standardHPP — other colours
ChemistryUV-stable polyurea, single componentPolyaspartic, two-component kit
Wet film over the FPUOne coat, up to 20 milsSet in our written specification
ColourMedium greyTinted on site to any colour
Elongation648%20% — a hard topcoat, not a crack-bridging membrane
Tack-free2–3 hours (20 °C, 50% RH)About 1 hour (23 °C, 50% RH)
Drying and cureThrough-dry in about 9 hours; full cure in 24–48 hoursLight foot traffic in 3–4 hours; protect from rain for at least 6–12 hours; full cure in 5–7 days
Choose it whenGrey suits the roof: our standard topAnother colour is wanted, or light foot traffic is needed within hours

What we won’t do

Where RMS is the wrong answer.

It is not a traffic surface. A roof terrace, or a walkway route to rooftop equipment that carries regular foot traffic, takes ResinTech PTS+, our pedestrian traffic system, and rooftop parking takes VTS-D+. If only part of a roof is walked on regularly, each area is specified separately.

It does not fix a roof that holds water. RMS needs positive drainage, and service under ponding or standing water is not covered, so the drainage comes first. Nor does the field membrane bridge expansion or active movement joints on its own: those get their own detail, which is the work on our expansion joints page.

RMS does not cover new wood or plywood roof decks; if yours is one, contact us to assess it. RMS is not for pools, tanks, potable water or submerged service. And we do not promise that it will bond to a particular existing roof before we have tested it: every existing roof gets an inspection and an adhesion test patch first.

Questions we get asked

Flat roof coating FAQs

Can you coat over our existing flat roof instead of replacing it?

It can be, if the existing roofing is sound, dry and firmly bonded to the deck, and the roof drains. Wet or deteriorated areas, splits, blisters and open laps are repaired first, and an adhesion test patch decides whether the membrane bonds to your roof. We inspect the roof and test it before we quote the full job, and if the roof is not a candidate we will tell you.

Do you also replace flat roofs?

Yes. Where the existing roofing has failed across the field, or a roof is not a candidate for restoration, we provide torch-on roofing instead. The inspection and the test patch decide which a roof needs.

Which existing roof types can RMS go over?

We do not promise that in advance. Every existing roof is inspected and test-patched, and the roof type is confirmed with ResinTech before the full application is quoted. The test patch is what tells us whether the system bonds to your roof, not a list of roof types.

Can RMS go on a new concrete roof deck?

Yes. A new concrete roof deck takes RMS with the reinforcing fabric over the full surface, with or without occupied space below. The concrete needs a minimum 28-day cure and has to be sound, clean and dry; a primer is used only where the substrate calls for one.

Can we use the roof as a terrace or walk on it?

RMS is built for roofs that carry no regular traffic. A roof terrace, or a walkway route to rooftop equipment that gets regular foot traffic, takes the ResinTech PTS+ pedestrian traffic system instead, and rooftop parking takes VTS-D+. If only part of the roof is walked on regularly, tell us and each area is specified separately.

What is the difference between the PPM and HPP top membranes?

PPM is our standard top: a UV-stable polyurea in medium grey, one coat of up to 20 mils wet film. HPP is the alternative for any other colour: a polyaspartic that is tack-free in about an hour, takes light foot traffic in 3 to 4 hours and can be tinted to any colour, but it is a hard topcoat rather than a crack-bridging membrane. In both cases the FPU coats and the fabric underneath are the waterproofing membrane.

What happens if water ponds on the roof?

RMS needs positive drainage. Service under ponding or standing water is not covered by the system data sheet, so a roof that holds water after rain has its drainage corrected first, or it is not a candidate for a coating.

Can RMS go on a new wood or plywood roof deck?

New wood and plywood roof decks are not covered by the RMS data sheet. Contact us to assess the deck and we will tell you what it needs.

How is a roof priced?

After an inspection. The size of the roof, the condition of the existing roofing, the amount of detailing at drains, upstands and penetrations, and access to the roof are what set the price, so we do not quote a blind rate per square foot.

Roof assessment request

Tell us about the roof.

The more of this you fill in, the more useful our first reply. The existing roof type helps us plan the visit; the test patch is what decides whether RMS bonds to it. If water is coming in right now, call (604) 968-2040 instead — that is faster than any form.

Photographs help most: the whole roof, the drains, the edges and any stains inside. Reply to our response with them attached, or call (604) 968-2040.

Keep reading

Related pages

Flat roofing

Restoration, replacement and repairs, and how we choose between them.

Learn more →

Torch-on roofing

New torch-on roofs and replacement where the existing roofing has failed.

Learn more →

Restore or replace

The four questions that decide whether a commercial flat roof can be restored.

Learn more →

Expansion joints

Movement joints, which a roof membrane must not bridge on its own.

Learn more →

Roof assessments

Send us the roof. We'll tell you if it can be restored.

Photographs and a rough area are enough to start. We'll inspect it, test-patch it, and tell you what it actually needs.

Main (604) 968-2040
Second (604) 230-0256
estimating@westpacificcoatings.com